Schedule Variance (SV)
Description
This metric gives the variation of actual schedule vs. the planned schedule. This is calculated for each project – stage wise
Formula
SV = [(Actual no. of days – Planned no. of days) / Planned no. of days] * 100
Metric Representation
Percentage
Calculated at
Stage completion
Calculated from
Software Project Plan for planned number of days for completing each stage and for actual number of days taken to complete each stage